How to Terminate a Redevelopment Agreement with a Builder in Maharashtra
When a builder halts construction, defaults on transit rent, or misses statutory deadlines, members of a housing society are not trapped. Under the Maharashtra Co-operative Societies Act, 1960 and consistent Bombay High Court rulings, the general body holds the legal right to terminate the contract, cancel the power of attorney, and reclaim their property.
Sign up to easily get answers to your legal questions
Create an account and ask about your own situation. You get a clear answer, and you stay aware of the rules, deadlines, and next steps that apply where you live.
Sign upWhat the law says about terminating redevelopment in Maharashtra
In Maharashtra, the relationship between a co-operative housing society (CHS) and a developer is governed by the Development Agreement, the Maharashtra Co-operative Societies Act, 1960 (MCS Act), and statutory directives issued under Section 79A. Under Section 72 of the MCS Act, the supreme authority of the society vests strictly in the General Body of its members, not the Managing Committee alone. When a developer breaches fundamental obligations—such as failing to pay monthly transit rent, failing to furnish the mandated bank guarantee under the Government Resolution dated July 4, 2019, or abandoning construction—the society is legally entitled to call off the transaction.
The Bombay High Court has repeatedly reinforced this autonomy (including in landmark rulings like Jal Ratan Deep CHS Ltd. v. Kumar Builders Mumbai Reality Pvt. Ltd. and Shubham Builders v. Kanchan Villa CHS Ltd.). The courts have held that where a developer demonstrates persistent non-performance and the society loses confidence, the society cannot be coerced into continuing the redevelopment project. Furthermore, under the Specific Relief Act, 1963, courts generally decline to grant injunctions or specific performance in favor of a defaulting developer to restrain a society from completing its project through alternative avenues.
The procedural gauntlet: Notice, cure periods, and the SGM resolution
A termination cannot be executed arbitrarily; strict compliance with procedural due process protects the society against subsequent litigation. Almost every registered Development Agreement contains a termination clause prescribing a formal notice of default and a cure period (typically 30 to 90 days) during which the builder is called upon to remedy specific breaches.
If the developer fails to cure the defaults within the notice window, the society must convene a Special General Body Meeting (SGM) following the notice requirements outlined in its model bye-laws and Section 79A directives. The General Body must pass a clear resolution resolving to terminate the Development Agreement, revoke all associated Powers of Attorney, and forfeit or adjust security deposits or bank guarantees where applicable. A detailed record of attendance, video recording of the proceedings (as encouraged under Section 79A guidelines), and exact voting counts must be preserved as crucial evidentiary backing.
Revoking the Power of Attorney and securing the development site
Executing a termination letter alone is insufficient if the developer still holds a registered General Power of Attorney (GPA). Even where a GPA is drafted as 'irrevocable', settled law under the Powers of Attorney Act, 1882 and Section 201 of the Indian Contract Act establishes that when the underlying contract is terminated for breach, the agency is terminated as well. The society must execute a formal, registered Deed of Revocation of Power of Attorney before the Sub-Registrar of Assurances.
Simultaneously, the society must issue public notices in both English and Marathi newspapers stating that the developer's authority has ceased, and notify the local planning authority (such as BMC, MMRDA, or PMC) to revoke or withhold further building permissions, Commencement Certificates (CC), or Intimation of Disapproval (IOD) in the builder's name. If the project is registered with MahaRERA, the society must address the regulatory framework under Sections 7 and 8 of the Real Estate (Regulation and Development) Act, 2016 to revoke the registration and seek takeover or self-redevelopment permission.
Navigating this process requires meticulous documentation and procedural exactness. You can use Caunsel to research relevant Bombay High Court precedents, store and track your society's notices and minutes in an organized digital case file, or consult an independent property lawyer to evaluate your next move before issuing notices.
Steps
- Compile comprehensive evidence of the builder's material breaches, including rent arrears, expired municipal permits (IOD/CC), project stagnation, or absent bank guarantees.
- Issue a formal legal notice through your society's advocate detailing every contractual breach and granting the developer the mandatory cure period (usually 30–90 days) to rectify them.
- Convene a Special General Body Meeting (SGM) under Section 79A directives and society bye-laws, passing a recorded resolution to terminate the Development Agreement and revoke the Power of Attorney.
- Execute and register a Deed of Revocation of the Power of Attorney with the Sub-Registrar of Assurances and publish public notices in Marathi and English newspapers.
- Formally notify the municipal corporation (e.g., BMC), the Deputy Registrar of Co-operative Societies, and MahaRERA of the termination to freeze ongoing approvals and prevent third-party rights from being created.
Common mistakes
- Terminating through a Managing Committee decision without convening an SGM and securing a General Body resolution.
- Failing to issue a contractually compliant cure notice before delivering the final termination letter.
- Issuing a termination notice without immediately executing and registering a Deed of Revocation for the General Power of Attorney.
- Neglecting to alert the planning authority (e.g., BMC) and MahaRERA, allowing the defaulting builder to continue selling units or dealing with third parties.
Questions people ask
Can the builder obtain an injunction to stop our society from terminating the agreement?
Under established Bombay High Court rulings and Section 14 and 41 of the Specific Relief Act, 1963, courts generally do not force an unwilling housing society into specific performance with a defaulting builder, especially where the builder failed to pay transit rent or progress the construction. However, the society must strictly adhere to procedural rules to prevent interim stays.
How can the society recover unpaid transit rent after termination?
The society can invoke the builder's bank guarantee if one was submitted under the Section 79A guidelines. If no liquid guarantee exists, the society can pursue recovery through arbitration proceedings (if stipulated in the agreement), Section 91 dispute proceedings before the Co-operative Court, or a summary commercial suit in civil court.
Does the society need permission from the Deputy Registrar or MahaRERA before terminating?
The General Body has the inherent right to terminate the contract for cause. However, intimation to the Deputy Registrar ensures administrative compliance under Section 79A. If the project is registered with MahaRERA and involves third-party allottee rights in the sale component, the society must submit an application under Sections 7 and 8 of RERA to regularize the deregistration or transfer of development rights.
Ask Caunsel to review your society's redevelopment termination clause or connect your managing committee with an independent property lawyer in Maharashtra.
Research it with the advisor, keep documents in a case, or talk to an independent lawyer. Start a subscription for AI tools.
General information only, last updated 2026-10-18. Caunsel is not a law firm and does not practise law. AI answers and this guide are not legal advice. Verify filings, deadlines, and statutes with a licensed lawyer in Maharashtra, India.